[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908192,587,1,"单选题","(2014年)建设工程组织流水施工时，某施工过程（专业工作队）在单位时间内完成的工程量称为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","流水节拍",false,{"key":16,"text":17,"correct":14},"B","流水步距",{"key":19,"text":20,"correct":14},"C","流水节奏",{"key":22,"text":23,"correct":24},"D","流水能力",true,"该题主要考察的是：流水施工参数 流水强度是指流水施工的某施工过程（队）在单位时间内所完成的工程量，也称为流水能力或生产能力。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]