[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908191,587,1,"单选题","(2016年)某工程划分为3个施工过程，4个施工段组织加快的成倍节拍流水施工，流水节拍分别为4天、6天和4天，则需要派出()个专业工作队。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","3","该题主要考察的是：有节奏流水施工，有节奏流水施工是指在组织流水施工时，每一个施工过程在各施工段上的流水节拍都各自相等的流水施工。K=2，施工队数=4÷2+6÷2+4÷2=7个。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]