[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908190,587,1,"单选题","(2015年)某工程划分为3个施工过程、4个施工段组织固定节拍流水施工，流水节拍为5天，累计间歇时间为2天，累计提前插入时间为3天，该工程流水施工工期为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","29",true,{"key":16,"text":17,"correct":18},"B","30",false,{"key":20,"text":21,"correct":18},"C","34",{"key":23,"text":24,"correct":18},"D","35","本题考查的是流水施工的基本组织方式。T= (3+4-1)×5+2-3=29天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]