[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908188,587,1,"单选题","(2010年)某分部工程划分为3个施工过程、4个施工段。组织成倍节拍流水施工，流水节拍分别为6，4，4d，则专业工作队数为()个。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","7",true,"具体计算步骤为：①计算流水步距。流水步距等于流水节拍的最大公约数，即：K=min[6，4，4]=2；②确定专业工作队数目。每个施工过程成立的专业工作队数可按公式计算：bj=tj\u002FK，在本题中，各施工过程的专业工作队数目分别为：bI=tI\u002FK=6\u002F2=3；bⅡ=tⅡ\u002FK=4\u002F2=2;bⅢ=tⅢ\u002FK=4\u002F2=2。因此，参与该工程流水施工的专业工作队总数n“=∑bj=(3+2+2)=7。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]