[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908184,587,1,"单选题","(2012年)某分部工程划分为两个施工过程、3个施工段组织流水施工，流水节拍分别为3、4、2d和3、5、4d，则流水步距为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","(在非节奏流水施工中， 通常采用累加数列错位相减取大差法计算流水步距。由于这种方法是由潘特考夫斯基（译音）首先提出的， 故又称为潘特考夫斯基法。这种方法简捷、准确， 便于掌握。累加数列错位相减取大差法的基本步骤如下： (1）对每一个施工过程在各施工段上的流水节拍依次累加， 求得各施工过程流水节拍的累加数列； (2）将相邻施工过程流水节拍累加数列中的后者错后一位， 相减后求得一个差数列； (3）在差数列中取最大值， 即为这两个相邻施工过程的流水步距。本题流水步距=max{3，4，1，-12}=4(d)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]