[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908176,587,1,"单选题","（2017年考题）编制单位工程施工进度计划时,确定工作项目持续时间需要考虑每班工人数量、限定每班工人数量上限的因素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作项目工程量",false,{"key":16,"text":17,"correct":14},"B","最小劳动组合",{"key":19,"text":20,"correct":14},"C","人工产量定额",{"key":22,"text":23,"correct":24},"D","最小工作面",true,"最小工作面限定了每班安排人数的上限。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]