[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908175":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908175,587,1,"单选题","(2015年)下列控制措施中，属于工程项目目标被动控制措施的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","制定实施计划时，考虑影响目标实现和计划实施的不利因素",false,{"key":16,"text":17,"correct":14},"B","说明和揭示影响目标实现和计划实施的潜在风险因素",{"key":19,"text":20,"correct":14},"C","制定必要的备用方案，以应对可能出现的影响目标实现的情况",{"key":22,"text":23,"correct":24},"D","跟踪目标实施情况，发现目标偏离时及时采取纠偏措施",true,"本题考查的是工程项目目标控制的内容、措施和方法。被动控制是指发现问题，找出偏差，寻求并确定解决问题和纠正偏差的方案，然后再回送给计划实施系统付诸实施，使得计划目标一旦出现偏离就能得以纠正。被动控制是一种反馈控制；属于事中事后控制。选项D属于被动控制，其它选项都是主动控制。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]