[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908173,587,1,"单选题","(2010年)下列方法中，可同时用来控制工程造价和工程进度的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","S曲线和直方图法",false,{"key":16,"text":17,"correct":14},"B","直方图和控制图法",{"key":19,"text":20,"correct":14},"C","排列图法和香蕉曲线法",{"key":22,"text":23,"correct":24},"D","香蕉曲线法和S曲线法",true,"对一个工程项目而言，如果以横坐标表示时间，纵坐标表示累计完成的工程数量或造价，即可形成一条形如“S”的曲线，所以S曲线可用于控制工程造价和工程进度。香蕉曲线是由两条S曲线组合在一起，因而香蕉曲线同样可用来控制工程造价和工程进度。香蕉曲线法原理与S曲线法的原理基本相同，区别在于它是以工程网络计划为基础绘制的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]