[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908171":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908171,587,1,"单选题","(2013年)下列工程项目目标控制方法中，可用来找出工程质量主要影响因素的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直方图法",false,{"key":16,"text":17,"correct":14},"B","鱼刺图法",{"key":19,"text":20,"correct":21},"C","排列图法",true,{"key":23,"text":24,"correct":14},"D","S曲线法","该题主要考察的是：排列图法，排列图又叫主次因素分析图或帕累特图，是用来寻找影响工程（产品）质量主要因素的一种有效工具。排列图由两个纵坐标、一个横坐标、若干个直方图形和一条曲线组成。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]