[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908169,587,1,"单选题","(2009年)作为施工承包单位计划体系的重要内容，项目管理实施规划应由()编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","企业管理层在投标之前",false,{"key":16,"text":17,"correct":14},"B","项目经理部在投标之前",{"key":19,"text":20,"correct":14},"C","企业管理层在开工之前",{"key":22,"text":23,"correct":24},"D","项目经理部在开工之前",true,"项目管理实施规划是在开工之前由施工项目经理组织编制， 并报企业管理层审批的工程项目管理文件。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]