[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908163,587,1,"单选题","(2011年)下列工程项目目标控制方法组中，控制的原理基本相同、目的也相同的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","香蕉曲线法和S曲线法",true,{"key":16,"text":17,"correct":18},"B","网络计划法和香蕉曲线法",false,{"key":20,"text":21,"correct":18},"C","排列图法和网络计划法",{"key":23,"text":24,"correct":18},"D","S曲线法和排列图法","S曲线可用于控制工程造价和工程进度。香蕉曲线法的原理与S曲线法的原理基本相同， 其主要区别在于： 香蕉曲线是以工程网络计划为基础绘制的。与S曲线法相同， 香蕉曲线同样可用来控制工程造价和工程进度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]