[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908162,587,1,"单选题","(2012年)下列工程项目目标控制方法中，可用来判断工程造价偏差的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制图法",false,{"key":16,"text":17,"correct":14},"B","鱼刺图法",{"key":19,"text":20,"correct":21},"C","S曲线法",true,{"key":23,"text":24,"correct":14},"D","网络计划法","S曲线可用于控制工程造价和工程进度。其控制程序如下：(3）将实际S曲线与计划S曲线进行比较，以此判断工程进度偏差或造价偏差。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]