[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908154,587,1,"单选题","（2017年考题）下列计划表中,属于建设单位计划体系中工程项目建设总进度计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","年度计划项目表",false,{"key":16,"text":17,"correct":14},"B","年度建设资金平衡表",{"key":19,"text":20,"correct":21},"C","投资计划年度分配表",true,{"key":23,"text":24,"correct":14},"D","年度设备平衡表","工程项目建设总进度计划表格部分包括：工程项目一览表、工程项目总进度计划、投资计划年度分配表和工程项目进度平衡表。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]