[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908148,587,1,"单选题","(2009年)建设工程采用CM承包模式时，CM单位有代理型和非代理型两种。工程分包商的签约对象是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","代理型为业主，非代理型为CM单位",true,{"key":16,"text":17,"correct":18},"B","代理型为CM单位，非代理型为业主",false,{"key":20,"text":21,"correct":18},"C","无论代理型或非代理型，均为业主",{"key":23,"text":24,"correct":18},"D","无论代理型或非代理型，均为CM单位","2) CM 单位有代理型（Agency）和非代理型（ Non-Agency）两种。代理型的CM单位不负责工程分包的发包， 与分包单位的合同由建设单位直接签订。而非代理型的CM单位直接与分包单位签订分包合同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]