[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908132":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908132,587,1,"单选题","(2018年)为了保护环境，在项目实施阶段应做到“三同时”。这里的“三同时”是指主体工程与环保措施工程要（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","同时施工、同时验收、同时投入运行",false,{"key":16,"text":17,"correct":14},"B","同时审批、同时设计、同时施工",{"key":19,"text":20,"correct":21},"C","同时设计、同时施工、同时投入运行",true,{"key":23,"text":24,"correct":14},"D","同时施工、同时移交、同时使用","本题考查工程项目管理的任务——环保与节能。在项目实施阶段，必须做到 “三同时”，即主体工程与环保措施工程同时设计、同时施工、同时投入运行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]