[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908114,587,1,"单选题","(2014年)根据《国务院关于投资体制改革的决定》，对于采用投资补助方式的政府投资项目，政府需要审批的文件是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","可行性研究报告",{"key":19,"text":20,"correct":21},"C","资金申请报告",true,{"key":23,"text":24,"correct":14},"D","初步设计和概算","本题考查的是项目投资决策管理制度。对于采用投资补助、转贷和贷款贴息方式的政府投资项目，则只审批资金申请报告。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]