[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908078,587,1,"单选题","（2019年）某通过招投标订立的政府采购合同金额为200万元，合同履行过程中需追加与合同标的相同的货物，在其他合同条款不变且追加合同金额最高不超过( )万元时，可以签订补充合同采购。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","20",true,{"key":20,"text":21,"correct":14},"C","40",{"key":23,"text":24,"correct":14},"D","50","经采购人同意，中标、成交供应商可依法采取分包方式履行合同。政府采购合同履行中，采购人需追加与合同标的相同的货物、工程或服务的，在不改变合同其他条款的前提下，可以与供应商协商签订补充合同，但所有补充合同的采购金额不得超过原合同采购金额的10%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]