[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908046,587,1,"单选题","(2014年)根据《建设工程安全生产管理条例》，建设工程安全作业环境及安全施工措施所需费用，应当在编制（）时确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":18},"B","工程概算",true,{"key":20,"text":21,"correct":14},"C","施工图预算",{"key":23,"text":24,"correct":14},"D","施工组织设计","该题主要考察的是：建设单位的安全责任 建设单位在编制工程概算时，应当确定建设工程安全作业环境及安全施工措施所需费用；在申请领取施工许可证时，应当提供建设工程有关安全施工措施的资料。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]