[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908044,587,1,"单选题","(2013年)根据《建设工程安全生产管理条例》，建设单位将保证安全施工的措施报送建设行政主管部门或者其他有关部门备案的时间是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设工程开工之日起15日内",false,{"key":16,"text":17,"correct":14},"B","建设工程开工之日起30日内",{"key":19,"text":20,"correct":21},"C","开工报告批准之日起15日内",true,{"key":23,"text":24,"correct":14},"D","开工报告批准之日起30日内","该题主要考察的是：建设单位的安全责任 依法批准开工报告的建设工程，建设单位应当自开工报告批准之日起15日内，将保证安全施工的措施报送建设工程所在地的县级以上地方人民政府建设行政主管部门或者其他有关部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]