[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908042,587,1,"单选题","(2016年)根据《建筑法》，获取施工许可证后因故不能按期开工的，建设单位应当申请延期，延期的规定是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以两次为限，每次不超过2个月",false,{"key":16,"text":17,"correct":14},"B","以三次为限，每次不超过2个月",{"key":19,"text":20,"correct":21},"C","以两次为限，每次不超过3个月",true,{"key":23,"text":24,"correct":14},"D","以三次为限，每次不超过3个月","该题主要考察的是：施工许可证的有效期限 ，建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]