[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908037,587,1,"单选题","(2018年)美国工程造价估算中，材料费和机械费用估算的基础是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现行市场行情或市场租赁价",true,{"key":16,"text":17,"correct":18},"B","联邦政府公布的商业信息价",false,{"key":20,"text":21,"correct":18},"C","现行材料及设备供应商报价",{"key":23,"text":24,"correct":18},"D","预计项目实施时的市场价","造价工程师的动态估价：美国工程造价估算中的人工费由基本工资和附加工资两部分组成。其中，附加工资项目包括管理费、保险金、劳动保护金、退休金、税金等。材料费和机械使用费均以现行的市场行情或市场租赁价作为造价估算的基础，并在人工费、材料费和机械使用费总额的基础上按照一定的比例（一般为 10%左右）再计提管理费和利润。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]