[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908034,587,1,"单选题","(2012年)美国建筑师学会(AI A)合同条件体系中的核心是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","财务管理表格",false,{"key":16,"text":17,"correct":14},"B","专用条件",{"key":19,"text":20,"correct":14},"C","合同管理表格",{"key":22,"text":23,"correct":24},"D","通用条件",true,"合同条件体系的核心是“通用条件”。采用不同的计价方式时，只需选用不同的“协议书格式”与“通用条件”结合。AIA合同条件主要有总价、成本补偿及最高限定价格等计价方式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]