[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908025,587,1,"单选题","(2015年)生产性建设项目总投资由()两部分组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑工程投资和安装工程投资",false,{"key":16,"text":17,"correct":14},"B","建安工程投资和设备工器具投资",{"key":19,"text":20,"correct":21},"C","固定资产投资和流动资产投资",true,{"key":23,"text":24,"correct":14},"D","建安工程投资和工程建设其他投资","本题考查的是工程造价相关概念。生产性建设项目总投资包括固定资产投资和流动资产投资两部分；非生产性建设项目总投资只包括固定资产投资，不含流动资产投资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]