[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908024,587,1,"单选题","(2011年)生产性建设项目的总投资由()两部分构成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定资产投资和流动资产投资",true,{"key":16,"text":17,"correct":18},"B","有形资产投资和无形资产投资",false,{"key":20,"text":21,"correct":18},"C","建筑安装工程费用和设备工器具购置费用",{"key":23,"text":24,"correct":18},"D","建筑安装工程费用和工程建设其他费用","建设项目总投资是指为完成工程项目建设， 在建设期（预计或实际）投入的全部费用总和。建设项目按用途可分为生产性建设项目和非生产性建设项目。生产性建设项目总投资包括固定资产投资和流动资产投资两部分；非生产性建设项目总投资只包括固定资产投资， 不含流动资产技资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]