[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908023,587,1,"单选题","(2013年)下列费用中，属于建设工程静态投资的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":18},"B","涨价预备费",false,{"key":20,"text":21,"correct":18},"C","建设期贷款利息",{"key":23,"text":24,"correct":18},"D","建设工程有关税费","该题主要考察的是：静态投资定义 静态投资是指不考虑物价上涨、建设期贷款利息等影响因素的建设投资。静态投资包括：建筑安装工程费、设备和工器具购置费、工程建设其他费、基本预备费， 以及因工程量误差而引起的工程造价增减值等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]