[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908022,587,1,"单选题","(2016年)工程项目的多次计价是一个()的过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","逐步分解和组合，逐步汇总概算造价",false,{"key":16,"text":17,"correct":18},"B","逐步深化和细化，逐步接近实际造价",true,{"key":20,"text":21,"correct":14},"C","逐步分析和测算，逐步确定投资估算",{"key":23,"text":24,"correct":14},"D","逐步确定和控制，逐步积累竣工结算价","该题主要考察的是：工程项目的计价多次性，多次计价是一个逐步深入和细化，不断接近实际造价的过程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]