[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907982,587,1,"单选题","(2010年)按照优先性的原则，协调和平衡工期、质量、安全、环保与成本之间的对立统一关系，反映了( )造价管理的思想。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全寿命期",false,{"key":16,"text":17,"correct":18},"B","全要素",true,{"key":20,"text":21,"correct":14},"C","全过程",{"key":23,"text":24,"correct":14},"D","全方位","影响工程造价的因素很多。为此，控制建设工程造价不仅仅是控制建设工程本身的成本，还应同时考虑工期成本、质量成本、安全与环境成本的控制，从而实现工程造价、工期、质量、安全、环境的集成管理。全要素造价管理的核心是按照优先性的原则，协调和平衡工期、质量、安全、环保与成本之间的对立统一关系。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]