[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907979,587,1,"单选题","(2010年)在调查—分析—决策基础之上的偏离—纠偏—再偏离—再纠偏的工程造价控制属于()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","前馈控制",false,{"key":16,"text":17,"correct":14},"B","预防控制",{"key":19,"text":20,"correct":21},"C","被动控制",true,{"key":23,"text":24,"correct":14},"D","全过程控制","立足于调查—分析—决策基础之上的偏离—纠偏—再偏离—再纠偏的控制是一种被动控制，因为这样做只能发现偏离，不能预防可能发生的偏离。为尽可能地减少以至避免目标值与实际值的偏离，还必须立足于事先主动地采取控制措施，实施主动控制。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]