[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907978,587,1,"单选题","(2011年)建设工程全要素造价管理的核心是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程参建各方建立完善的工程造价管理协同工作机制",false,{"key":16,"text":17,"correct":18},"B","协调和平衡工期、质量、安全、环保与成本之间的对立统一关系",true,{"key":20,"text":21,"correct":14},"C","采取有效措施控制工程变更和索赔",{"key":23,"text":24,"correct":14},"D","做好前期策划和方案设计、实现建设工程全寿命期成本最小化","全要素造价管理的核心是按照优先性原则， 协调和平衡工期、质量、安全、环保与成本之间的对立统一关系。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]