[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},907976,587,1,"单选题","(2009年)对于政府投资项目而言，作为拟建项目工程造价最高限额的是经有关部门批准的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":18},"B","工程概算",true,{"key":20,"text":21,"correct":14},"C","施工图预算",{"key":23,"text":24,"correct":14},"D","承包合同价","(2）工程设计阶段：在限额设计、优化设计方案的基础上编制和审核工程概算、施工图预算。对于政府投资工程而言，经有关部门批准的工程概算，将作为拟建工程项目造价的最高限额。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]