[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907957,586,2,"多选题","（2020年真题）根据《房屋建筑与装饰工程量计算规范》（GB50854-2013），关于柱面抹灰工程量计算正确的为（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","柱面勾缝忽略不计",false,{"key":16,"text":17,"correct":14},"B","柱面抹麻刀石灰浆按柱面装饰抹灰编码列项",{"key":19,"text":20,"correct":21},"C","柱面一般抹灰按设计断面周长乘以高度以面积计算",true,{"key":23,"text":24,"correct":21},"D","柱面勾缝按设计断面周长乘以高度以面积计算",{"key":26,"text":27,"correct":21},"E","柱面砂浆找平按设计断面周长乘以高度以面积计算","CDE","P426-429 选项A错误，选项D正确，柱面勾缝，按设计图示柱断面周长乘高度以面积\"m2\"计算。 选项B错误，柱（梁）面抹石灰砂浆、水泥砂浆、混合砂浆、聚合物水泥砂浆、麻刀石灰浆、石膏灰浆等按柱（梁）面一般抹灰编码列项； 选项CE正确，柱面一般抹灰、柱面装饰抹灰、柱面砂浆找平层，按设计图示柱断面周长乘高度以面积\"m2”计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]