[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907955":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907955,586,2,"多选题","（2020年真题）根据《房屋建筑与装饰工程工程量》计算规范（GB50854-2013），土方工程工程量计算正确的为（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建筑场地厚度≤土300m的挖、填、运、找平，均按平整场地计算",true,{"key":16,"text":17,"correct":14},"B","设计底宽≤7m，底长>3倍底宽的土方开挖，按挖沟槽土方计算",{"key":19,"text":20,"correct":14},"C","设计底宽>7m，底长>3倍底宽的土方开挖，按一般土方计算",{"key":22,"text":23,"correct":24},"D","设计底宽≤7m，底长\u003C3倍底宽的土方开挖，按挖基坑土方计算",false,{"key":26,"text":27,"correct":24},"E","土方工程量均按设计尺寸以体积计算","ABC","P372-378 选项A正确，建筑物场地厚度小于或等于±300mm的挖、填、运、找平，应按平整场地项目编码列项。 选项B正确，选项C正确，选项D错误，底宽小于或等于7m，底长大于3倍底宽为沟槽；底长小于或等3倍底宽、底面积小于或等于150m2为基坑；超出上述范围则为一般土方。 选项E错误",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]