[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907950":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907950,586,2,"多选题","（2018年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），措施项目工程量计算有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","垂直运输按使用机械设备数量计算",false,{"key":16,"text":17,"correct":18},"B","悬空脚手架按搭设的水平投影面积计算",true,{"key":20,"text":21,"correct":18},"C","排水、降水工程量，按排水、降水日历天数计算",{"key":23,"text":24,"correct":18},"D","整体提升架按所服务对象的垂直投影面积计算",{"key":26,"text":27,"correct":18},"E","超高施工增加按建筑物超高部分的建筑面积计算","BCDE","垂直运输可按建筑面积计算也可按施工日期日历天数计算，以天位单位。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]