[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907940,586,2,"多选题","（2015年真题）某坡地建筑基础，设计基底垫层宽为8.0m，基础中心线长为22.0m，开挖深度为1.6m，地基为中等风化软岩，根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）规定，关于基础石方的项目列项或工程量计算正确的为（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按挖沟槽石方列项",false,{"key":16,"text":17,"correct":14},"B","按挖基坑石方列项",{"key":19,"text":20,"correct":21},"C","按挖一般石方列项",true,{"key":23,"text":24,"correct":21},"D","工程量为286.1m3",{"key":26,"text":27,"correct":14},"E","工程量为22.0m","CD","本题考查的是土石方工程。按设计图示尺寸沟槽（基坑）底面积乘以挖石深度以体积计算，单位：m3。沟槽、基坑、一般石方的划分为：底宽 3倍底宽为沟槽；底长\u003C3倍底宽且底面积\u003C150m2为基坑；超出上述范围则为一般石方。工程量：8×22×1.6=281.6m3。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]