[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907932,586,2,"多选题","（2019年真题）工程量计算规范中\"工作内容\"的作用有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","给出了具体施工作业内容",true,{"key":16,"text":17,"correct":14},"B","体现了施工作业和操作程序",{"key":19,"text":20,"correct":14},"C","是进行清单项目组价基础",{"key":22,"text":23,"correct":24},"D","可以按工作内容计算工程成本",false,{"key":26,"text":27,"correct":24},"E","反映了清单项目的质量和安全要求","ABC","工作内容是指为了完成工程量清单项目所需要发生的具体施工作业内容。工程量计算规范附录中给出的是一个清单项目所可能发生的工作内容，在确定综合单价时需要根据清单项目特征中的要求、具体的施工方案等确定清单项目的工作内容，是进行清单项目组价的基础。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]