[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907921":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907921,586,2,"多选题","（2016年真题）关于隧道工程喷射混凝土施工，说法正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","喷射作业混凝土利用率高",false,{"key":16,"text":17,"correct":18},"B","喷射作业区段宽度一般以1.5-2.0m为宜",true,{"key":20,"text":21,"correct":18},"C","喷射顺序应先墙后拱",{"key":23,"text":24,"correct":18},"D","喷射工作风压应随风管长度增加而增加",{"key":26,"text":27,"correct":14},"E","为了确保喷射效果风压通常应大于水压","BCD","（A）喷射混凝土施工回弹比较严重，混凝土利用率不高；（B）喷射作业区段的宽度，一般应以1.5?2.0m为宜；（C）对水平坑道，其喷射顺序为先墙后拱、自上而下；（D）水平输送距离每增加l00m，工作风压应提高0.08?0.lOMPa;倾斜向下喷射，每增加100m，工作风压应提高0.05?0.07MPa;垂直向上喷射每增加10m，工作风压应提高0.02?0.03MPa。(E)喷嘴处的水压必须大于工作风压。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]