[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907801":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907801,586,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013的有关规定，下列项目工程量清单计算时，以数量为计量单位的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","镜面玻璃",false,{"key":16,"text":17,"correct":18},"B","灯箱",true,{"key":20,"text":21,"correct":18},"C","金属旗杆",{"key":23,"text":24,"correct":14},"D","塑料装饰线",{"key":26,"text":27,"correct":18},"E","金属字","BCE","2020版教材P435 本题考查的是其他装饰工程。镜面玻璃按设计图示尺寸以边框外围面积计算。 灯箱按设计图示数量\"个\"计算。 金属旗杆按设计图示数量\"根\"计算。 塑料装饰线工程量按设计图示尺寸以长度\"m\"计算。 金属字按设计图示数量\"个\"计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]