[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907786":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907786,586,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013，计算措施项目工程量时，可以以面积计算的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","大型机械安拆",false,{"key":16,"text":17,"correct":14},"B","施工排水、降水",{"key":19,"text":20,"correct":14},"C","挑脚手架",{"key":22,"text":23,"correct":24},"D","超高施工增加",true,{"key":26,"text":27,"correct":24},"E","满堂脚手架","DE","2020版教材P440 本题考查的是措施项目。大型机械设备进出场及安拆，按使用机械设备的数量\"台·次\"计算。 施工排水、降水，按排、降水日历天数\"昼夜\"计算。 挑脚手架，按搭设长度乘以搭设层数以延长米计算。 超高施工增加，按建筑物超高部分的建筑面积“m2”计算。 满堂脚手架按搭设的水平投影面积计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]