[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907785":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907785,586,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013，计算现浇混凝土工程量时正确的工程量清单计算规则有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","现浇混凝土构造柱不扣除预埋铁件体积",true,{"key":16,"text":17,"correct":14},"B","无梁板的柱高自楼板上表面算至柱帽下表面",{"key":19,"text":20,"correct":21},"C","伸入墙体内的现浇混凝土梁头体积不计算",false,{"key":23,"text":24,"correct":21},"D","现浇混凝土墙中，墙垛及突出部分不计算",{"key":26,"text":27,"correct":14},"E","以水平投影面积计算时，现浇混凝土楼梯伸入墙体内部分不计算","ABE","2020版教材P392 本题考查的是混凝土及钢筋混凝土工程。选项C错误，伸入墙体内的现浇混凝土梁头并入梁体积计算； 选项D错误，现浇混凝土墙中，墙垛及突出部分并入墙体体积内计算。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]