[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907745":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907745,586,2,"多选题","桥梁承载结构的施工方法中，施工时不影响桥下交通的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预制安装法",false,{"key":16,"text":17,"correct":18},"B","悬臂施工法",true,{"key":20,"text":21,"correct":18},"C","转体施工法",{"key":23,"text":24,"correct":14},"D","顶推施工法",{"key":26,"text":27,"correct":14},"E","横移施工法","BC","预制安装法是指在预制工厂或在运输方便的桥址附近设置预制场进行梁的预制工作，然后采用一定的架设方法进行安装。悬臂施工法可不用或少用支架，施工不影响通航或桥下交通。 转体施工法施工期间不断航，不影响桥下交通，并可在跨越通车线路上进行桥梁施工。 顶推施工是在沿桥纵轴方向的台后设置预制场地，分节段预制，并用纵向预应力筋将预制节段与施工完成的梁体连成整体，然后通过水平千斤顶施力，将梁体向前顶推出预制场地。之后继续在预制场进行下一节段梁的预制，循环操作直至施工完成。 横向位移施工多用于正常通车线路上的桥梁工程的换粱。为了尽量减少交通的中断时间，可在原桥位旁预制并横移施工。 2020版教材P279-283",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]