[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907744":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907744,586,2,"多选题","沥青混凝土路面的初压和终压可选用的压路机械有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","光轮压路机",false,{"key":16,"text":17,"correct":18},"B","钢筒式压路机",true,{"key":20,"text":21,"correct":14},"C","振动压路机",{"key":23,"text":24,"correct":18},"D","关闭振动装置的振动压路机",{"key":26,"text":27,"correct":14},"E","手扶振动压路机","BD","2020版教材P275 本题考查的是路面施工。压实应按初压、复压、终压（包括成型）三个阶段进行。 初压应在混合料摊铺后较高温度条件下进行，不得产生摊移、开裂，压路机应从外侧向路中心碾压，应采用轻型钢筒式压路机或关闭振动装置的振动压路机碾压2遍； 复压应紧接在初压后进行，宜采用重型轮胎式压路机，也可采用振动压路机或钢筒式压路机，碾压遍数应经试压确定，不宜少于4~6遍； 终压应紧接在复压后进行。终压后选用双轮钢筒式压路机或关闭振动的振动压路机碾压，不宜少于2遍，并要求压后无轨迹。压路机应以慢而均匀的速度碾压。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]