[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907707":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907707,586,2,"多选题","土石方工程中，下列关于填方压实施工要求的说法中不正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","填充的边坡坡度越小越好",true,{"key":16,"text":17,"correct":18},"B","填方宜采用同类土填筑",false,{"key":20,"text":21,"correct":18},"C","基础的结构混凝土达到一定的强度后方可填筑",{"key":23,"text":24,"correct":18},"D","填方按设计要求预留沉降量",{"key":26,"text":27,"correct":14},"E","填方由下向上一次完成","AE","2020版教材P181 本题考查的是土石方工程施工技术。选项A错误，边坡坡度应根据土质、开挖深度、开挖方法、施工工期、地下水位、坡顶荷载及气候条件等因素确定。选项E错误，填方压实工程应由下至上分层铺填，分层压实。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]