[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907703":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907703,586,2,"多选题","下列对于屋面保温工程的描述正确的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","板状材料保温层采用干铺法施工时，相邻板块应错缝拼接",true,{"key":16,"text":17,"correct":14},"B","纤维材料保温层施工时，应避免重压，并应采取防潮措施",{"key":19,"text":20,"correct":14},"C","在浇筑泡沫混凝土时，泵送时应采取低压泵送",{"key":22,"text":23,"correct":14},"D","当设计有隔汽层时，先施工隔汽层，然后再施工保温层",{"key":25,"text":26,"correct":27},"E","泡沫混凝土应分层浇筑，一次浇筑厚度不宜超过300mm",false,"ABCD","2020版教材P254 本题考查的是建筑工程防水和保温工程施工技术。选项E错误，泡沫混凝土应分层浇筑，一次浇筑厚度不宜超过200mm。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]