[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907698":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907698,586,2,"多选题","现浇钢筋混凝土构件模板拆除的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","悬臂构件底模拆除时的混凝土强度应达设计强度的50％",false,{"key":16,"text":17,"correct":18},"B","后张预应力混凝土结构构件的侧模宜在预应力筋张拉前拆除",true,{"key":20,"text":21,"correct":14},"C","跨度大于8m的板拆除底模时的混凝土强度应达设计强度的75%",{"key":23,"text":24,"correct":14},"D","侧模拆除时混凝土强度须达设计混凝土强度的50％",{"key":26,"text":27,"correct":18},"E","一般是先拆非承重模板，后拆承重模板","BE","2020版教材P213 本题考查的是模板工程。选项A错误，悬臂构件底模拆除时的混凝土强度应达设计强度的100％ 选项C错误，跨度大于8m的板拆除底模时的混凝土强度应达设计强度的100% 选项D错误，侧模板拆除时的混凝土强度应能保证其表面及棱角不受损伤。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]