[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907692":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907692,586,2,"多选题","防止大体积混凝土浇筑后产生裂缝的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","采用矿渣水泥",true,{"key":16,"text":17,"correct":14},"B","加高效减水剂",{"key":19,"text":20,"correct":21},"C","加大浇筑速度",false,{"key":23,"text":24,"correct":14},"D","采用人工降温",{"key":26,"text":27,"correct":14},"E","加缓凝剂","ABDE","要防止大体积混凝土结构浇筑后产生裂缝，就要降低混凝土的温度应力，大体积混凝土施工温度控制应符合下列规定：①混凝土入模温度不宜大于30℃，混凝土浇筑体最大温升不宜大于50℃。 ②在覆盖养护或带模养护阶段，混凝土浇筑体表面以内40~100mm位置处的温度与混凝土浇筑体表面温度差值不宜大于25℃；结束覆盖养护或拆模后，混凝土浇筑体表面以内40~100mm位置处的温度与环境温度差值不应大于25℃； ③混凝土降温速率不宜大于2.0℃\u002Fd。为此应采取相应的措施有：应优先选用水化热低的水泥；在满足设计强度要求的前提下，尽可能减少水泥用量；掺入适量的粉煤灰（粉煤灰的掺量一般以15%~25%为宜）；降低浇筑速度和减小浇筑层厚度；采取蓄水法或覆盖法进行人工降温措施；必要时经过计算和取得设计单位同意后可留后浇带或施工缝分层分段浇筑。 2020版教材P200-244",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]