[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907441":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907441,586,2,"多选题","流沙能给施工带来很大困难，或直接影响工程建设及附近建筑物的稳定，流沙常用的处置方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","化学加固法",false,{"key":16,"text":17,"correct":18},"B","人工降低地下水位",true,{"key":20,"text":21,"correct":14},"C","爆炸法",{"key":23,"text":24,"correct":18},"D","打板桩",{"key":26,"text":27,"correct":14},"E","抛入大块石","BD","常用的处置方法有人工降低地下水位和打板桩等，特殊情况下也有采取化学加固法、爆炸法及加重法等。在基槽开挖的过程中局部地段突然出现严重流沙时，可立即抛入大块石等阻止流沙。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]