[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907380":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907380,586,2,"多选题","(2017年)地下工程喷射混凝土施工时，正确的工艺要求有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","喷射作业区段宽以1.5~2.0m 为宜",true,{"key":16,"text":17,"correct":14},"B","喷射顺序应先喷墙后喷拱",{"key":19,"text":20,"correct":14},"C","喷管风压随水平输送距离大而提高",{"key":22,"text":23,"correct":24},"D","工作风压通常应比水压大",false,{"key":26,"text":27,"correct":24},"E","为减少浆液浪费一次喷射厚度不宜太厚","ABC","喷射施工要按一定顺序有条不紊地进行。喷射作业区段的宽度，一般应以1.5~2.0m 为宜。对水平坑道，其喷射顺序为先墙后拱、自下而上；侧墙应自墙基开始，拱应自拱脚开始，封拱区宜沿轴线由前向后。当输送距离变化时，工作风压可参考以下数值：水平输送距离每增加100m，工作风压应提高0.08~0.10MPa；倾斜向下喷射，每增加100m，工作风压应提高0.05~0.07MPa；垂直向上喷射每增加10m，工作风压应提高0.02~0.03MPa 工程实践证明，喷嘴处的水压必须大于工作风压，并且压力稳定才会有良好的喷射效果。水压一般比工作风压大0.10MPa 左右为宜。一次喷射厚度太薄，喷射时骨料易产生大的回弹；一次喷射的太厚，易出现喷层下坠、流淌，或与基层面间出现空壳。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]