[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907379":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907379,586,2,"多选题","（2017年）地下连续墙开挖,对确定单元槽段长度因素说法正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","土层不稳定时,应增大槽段长度",false,{"key":16,"text":17,"correct":18},"B","附近有较大地面荷载时,可减少槽段长度",true,{"key":20,"text":21,"correct":14},"C","防水要求高时可减少槽段长度",{"key":23,"text":24,"correct":18},"D","混凝土供应充足时可选用较大槽段",{"key":26,"text":27,"correct":18},"E","现场起重能力强可选用较大槽段","BDE","当土层不稳定时，为防止槽壁坍塌，应减少单元槽段的长度,A 不对。防水要求高的应减少接头的数量，即增加槽段的长度，C 不对。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]