[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907376":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},907376,586,2,"多选题","(2016年)关于地下连续墙施工，说法正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","机械化程度高",true,{"key":16,"text":17,"correct":14},"B","强度大，挡土效果好",{"key":19,"text":20,"correct":21},"C","必须放坡开挖，施工土方量大",false,{"key":23,"text":24,"correct":14},"D","相邻段接头部位容易出现质量问题",{"key":26,"text":27,"correct":14},"E","作业现场容易出现污染","ABDE","选项A正确，地下连续墙施工全盘机械化，速度快、精度高，并且振动小、噪声低，适用于城市密集建筑群及夜间施工。选项B正确，具有多功能用途，如防渗、截水、承重、挡土、防爆等，由于采用钢筋混凝土或素混凝土，强度可靠，承压力大。选项C错误，开挖基坑无须放坡，土方量小，浇混凝土无须支模和养护，并可在低温下施工，降低成本，缩短施工时间。选项D、E正确，每段连续墙之间的接头质量较难控制，往往容易形成结构的薄弱点，制浆及处理系统占地较大，管理不善易造成现场泥泞和污染。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（土建）","建筑工程",0]