[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-907241":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},907241,586,1,"单选题","（2020年真题）根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），现浇混凝土雨篷工程量计算正确的为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","并入墙体工程量，不单独列项",false,{"key":16,"text":17,"correct":14},"B","按水平投影面积计算",{"key":19,"text":20,"correct":21},"C","按设计图示尺寸以墙外部分体积计算",true,{"key":23,"text":24,"correct":14},"D","扣除伸出墙外的牛腿体积","P389-408 雨篷、悬挑板、阳台板，按设计图示尺寸以墙外部分体积“m3”计算。包括伸出墙外的牛腿和雨篷反挑檐的体积。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]